71In an Information system. The is the bridge between hardware and people

Akeyboard

Binternet

Cdisk

Ddata

考无忧解析

在信息系统中。()是硬件和人之间的桥梁

A、键盘

B、互联网

C、磁盘

D、三维数据

考无忧参考答案:A

 

72Cloud-computing providers offer their services according to different models, which happen to form a stack , platform as a service (Paas), software as a service (SaaS)

Ahardware as a service (Haas)

Bnetwork as a service (NaaS)

Cinfrastructure as a service (IaaS)

Ddata as a service (DaaS)

考无忧解析

云计算供应商提供他们的“服务”,根据不同的类型,恰好形成(),平台即服务(PaaS),软件即服务(SaaS

A、硬件即服务(HAAS

B、网络作为一种服务(NAAS

C、基础设施即服务(IaaS

D、数据即服务(DaaS

考无忧参考答案:C

 

73、( estimating is a technique for estimating the duration or cost of an activity ou project using historical datafrom a similar activity or project.

AParametric

BAnalogous

CThree-point

DExpert judgment

考无忧解析

()估计是一项技术,用于估计活动的时间或成本,使用历史数据从类似的活动或项目。

A、参数

B、类比

C、三点

D、专家判断

考无忧参考答案:B

 

74Schedule compression shortens the project schedule without changing the project scope, to meet scheduleconstraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and

Afast tracking

Bwhat-if scenario analysis

Cresource leveling

Dcritical chain method

考无忧解析

进度压缩技术包括快速跟进

考无忧参考答案:A

 

75If the approved change requests have an effect on the project scope, then the corresponding componentdocuments and cost baselines, and of the project management plan. Are revised and reissued to reflect theapproved changes

Adeveloping baselines

Btesting baselines

Cschedule baselines

Dending baselines

考无忧解析

如果批准的变更请求对项目范围的影响,那么相应的组件文件和成本基线,和()的项目管理计划。修订再版反映批准的变更

A、发展基线

B、测试基线

C、进度基线

D、结束基线

考无忧参考答案:C