A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.There are some special activities called (72) . which are events that signify the ccomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73), whose purpose is to contain the various pieces of relevant information - feasibility assessments,schedules, needs analysis, and so forth - in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.
1.[单选题]A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.There are some special activities called (72) . which are events that signify the ccomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73), whose purpose is to contain the various pieces of relevant information - feasibility assessments,schedules, needs analysis, and so forth - in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.
A. Network Diagram
B.CPM
C.Gantt chart
D.PERT
2.[单选题]A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.There are some special activities called (72) . which are events that signify the ccomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73), whose purpose is to contain the various pieces of relevant information - feasibility assessments,schedules, needs analysis, and so forth - in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.
A.Structure Chan
B. Organizational Structure
C.Work Breakdown Structure
D.Functional decomposition diagram
3.[单选题]A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.There are some special activities called (72) . which are events that signify the ccomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73), whose purpose is to contain the various pieces of relevant information - feasibility assessments,schedules, needs analysis, and so forth - in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.
A.Gantt chart
B.Network Diagram
C.PERT
D.CPM
4.[单选题]A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.There are some special activities called (72) . which are events that signify the ccomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73), whose purpose is to contain the various pieces of relevant information - feasibility assessments,schedules, needs analysis, and so forth - in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.
A.feasibility checkpoints
B.milestones
C.iterations
D.phases
5.[单选题]A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.There are some special activities called (72) . which are events that signify the ccomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73), whose purpose is to contain the various pieces of relevant information - feasibility assessments,schedules, needs analysis, and so forth - in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.
A.statement of work
B.project planning
C.baseline plan
D.information system planning
参考答案:
D,C,A,B,C
解题思路:
(71) C: (72) B; (73) C; (74) D; (75) A。目前被广泛使用的一种项目管理技术就是工作分解结构(Work Breakdown Structure), 其目的是采用层次结构的方式,详细地描述为了达到项目的目标所需要进行的一些活动。在这些活动中有一些被称为里程碑(milestones)的特殊活动.这些活动中包含了标志项目的主要交付产品己经完成的事件•大多数系统开发方法都提供了基线计划(baseline plan),其目的是将一系列相关信息.如可行性评估、进度安排和需求分析等包含在一起,便于向项目的客户及相关团体展示。在项目管理中还用到了一些重要的网络图形。在对项目任务进行安排之前,可以使用PERT图清晰地展示这些任务之间的内在依赖关系。Gamt图通常应用于具有现实并行关系的任务的场合.
>>>立即刷题
相关动态
2017年上半年信息系统项目管理师综合知识真题 (41-49)
2018年信息系统项目管理师下午论文写作技巧
2016年下半年软考信息系统项目管理师历年真题上午综合知识(41-50)无答案版
2018信息系统项目管理师考试学习笔记:信息系统项目管理基础(2)
2018年信息系统项目管理师教程第3版目录列表
2017年河北信息系统项目管理师考试准考证打印时间
热点动态
2020年全国职称计算机考试和职称英语考試取消了吗?到底还考不考?
2020年全国计算机一级考试题型及分值
二级Ms Office全国通过率22%,真的很难吗?
【历年真题】2020年8月《12656毛泽东思想和中国特色社会主义理论体系》自考试卷(含答案)
2021年【历年真题】4月《12656毛泽东思想和中国特色社会主义理论体系》自考试卷(含答案)
【历年真题】2020年10月《12656毛泽东思想和中国特色社会主义理论体系》自考试卷(含答案)
QQ客服:蓝老师
QQ客服:侯老师
QQ客服:袁老师