1. Earned value management(EVM) integrates the scope baseline with the ( ) baseline ,along with schedule baseline,to form the performance baseline, which helps the project management…… 2. The ( ) creates opportunities for more direct Integration of the physical world into computer-based systems,resulting inefficiently improvements ,economic benefits,and reduced hum…… 3. ( ) is an open,distributed ledger that can record transactions between two parties efficiently and in a verifiable and permanent way. 4. ( ) are those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocated equitably over multiple projects by, some approved and doc…… 5. ( ) risks cannot be management proactively and therefore may be assigned a management reserve. 6. 质量保证成本属于质量成本中的( )成本。 7. 可用于评估组织内项目组合管理成熟度,用于识别组织目前的最佳实践能力和结果。 8. 根据项目进度基准和成本基准制定质量测量指标,于( )阶段的工作内容。 9. 在A项目的质量例会中,质量经理发现监控模块bug修复时间较长,有测量指标超出临界线,质量经理决定再观察几天。本次质量控制的输出一定包括()。 10. ( )属于系统测试执行过程中的工作效率指标。 11. 项目集指导委员会的主要职责包括( )、项目集批准和启动。 12. 关于成本估算的描述,正确的是( )。 13. 在确定项目合同类型时,如果项目工作范围很明确且风险不大,建议使用( ) 。 14. 关于成本基准的描述,不正确的是( )。 15. ( )战略组织模式的特点是组织高层从如何动员全体成员都参与战略实施活动的角度来考虑战略的指定和执行。 16. 在马斯洛需求层次理论中,位于金字塔结构第3层的是( )需求。 17. 配置管理工作中,确定配置项的所有者及其责任、确定配置项进入配置管理的时间和条件是( )的工作内容。 18. 根据供方选择标准,选择最合适的供方属于( )阶段的工作。 19. ( )是一种支持结构化程序设计的流程设计工具。它的执行顺序是从最左主干线的上端结点的上编结点开始,自上而下依次执行。 20. 关于配置控制委员会(CCB)的说法,正确的是()。
×
微信扫一扫
快速购买